UTAH'S SMALL-FOOTPRINT DRILLING SPECIALISTLet’s talk: (385) 367-4955 ↗
← All projects

PAYSON, UTAH · ELECTRICAL CONDUIT

Payson driveway.
Electrical conduit bore.

A new underground route.
Less disruption across the driveway.

PROJECT OVERVIEW

A short crossing.
A practical solution.

A residential property in the Payson / West Mountain area needed a 2-inch electrical conduit sleeve beneath an existing concrete driveway. Chamba Trenchless completed the crossing using compact, pit-launched horizontal directional drilling.

The recorded bore path measured approximately 40.5 feet. The installation created a route below the concrete without a continuous open trench across the driveway.

METHODPit-launched HDDAPPLICATIONElectrical conduit sleeveSITE PRIORITYLimit driveway disturbance
Overhead view of the concrete driveway, launch pit, excavator and support equipment at the Payson conduit project.
An overhead view of the driveway crossing and compact launch area beside the concrete.
40.5 ftApproximate recorded bore path
2 inElectrical conduit sleeve
1 dayField installation
Payson, UTWest Mountain area

THE CHALLENGE

Existing concrete.
A sloped driveway.

The crossing followed a sloped section of driveway between the drill-side working area and the house side. The job called for a short underground route while keeping excavation concentrated around the access areas.

Instead of opening a continuous trench through the concrete crossing, the crew worked from a compact launch pit beside the driveway and drilled beneath it.

OUR SCOPE

Compact setup.
Conduit below the concrete.

Chamba brought its pit-launched drill and excavator to complete the electrical sleeve crossing on Saturday, November 14.

  • Positioned the drilling equipment in a launch excavation beside the driveway.
  • Completed the directional bore beneath the concrete crossing.
  • Installed the 2-inch electrical conduit sleeve.
  • Recorded the bore path and retained job-site photos for the project record.

THE RESULT

A route below.
Less excavation across the driveway.

The electrical sleeve crossing was completed in one field day. A compact drilling setup made this small residential installation practical without a continuous open trench across the driveway.

  • 2-inch electrical conduit sleeve installed.
  • Approximately 40.5 feet of recorded bore path.
  • Installation beneath an existing concrete driveway.
  • Field work completed November 14, 2026.

Planning an electrical conduit crossing?

Explore our electrical conduit boring services

LET’S TALK ABOUT YOUR NEXT BORE

A small job deserves
a great drilling partner.

Tell us about your project